[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1022640,751,1,"单选题","()容量的A值小于10的发电机，应装设定时限和反时限两部分组成的转子表层过负荷保护，定时限部分保护动作于信号’反时限部分动作于解列或程序跳闸。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","250MW及以上；",false,{"key":16,"text":17,"correct":18},"B","100MW及以上；",true,{"key":20,"text":21,"correct":14},"C","200MW及以上；",{"key":23,"text":24,"correct":14},"D","300MW及以上。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]