[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1022591,751,1,"单选题","对某电力系统装设的低频减载装置进行整定，确定各定值。 带较长时间的后备段，最小动作时间为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2~5s；",true,{"key":16,"text":17,"correct":18},"B","5~7s；",false,{"key":20,"text":21,"correct":18},"C","7~9s；",{"key":23,"text":24,"correct":18},"D","10~15s。","根据GB\u002FT14285—20064.2.3.1条， 答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]