[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1022516,751,1,"单选题","当机组采用分散控制系统时，电气部分控制以下说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电气和热控自动化水平宜协调一致，其监控范因按单元机组划分，可保留必要的紧急硬手操设备，继电保护、自动准同步、自动电压调节、故障录波和厂用电源快速切换等功能应有专用装置实现；",true,{"key":16,"text":17,"correct":18},"B","电气和热控自动化水平宜协调一致，其监控范围以需电气控制的设备为准，继电保护、自动准同步、自动电压调节、故障录波和厂用电源快速切换等功能应有专用装里实现；",false,{"key":20,"text":21,"correct":18},"C","电气和热控自动化水平宜协调一致，其监控范围以发电机为单元监控，控制、继电保护自动准同步、自动电压调节、故障录波和厂用电源快速切换等功能由各自系统完成；",{"key":23,"text":24,"correct":18},"D","电气和热控自动化水平宜协调一致，应保留其硬手操设备，继电保护、自动准同步、自动电压调节、故障录波和厂用电源快速切换等功能由专用装置完成，","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]