[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022466":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1022466,751,1,"单选题","下列不符合发电机顺序控制规定的要求的是(）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发电机变压器组顺序控制时应与整套炉、机、电顺序控制相配合；",false,{"key":16,"text":17,"correct":14},"B","顺序控制应能与软手操实现无扰动切换；",{"key":19,"text":20,"correct":14},"C","机组的启停过程应与厂用系统的切换相配合；",{"key":22,"text":23,"correct":24},"D","发电机变压器组由DCS顺控时，宜设里手动准同步。",true,"",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]