[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1022408,751,1,"单选题","某电厂有两台300MW机组，采用发电机变压器组向500kV系统送电。 主接线为一个半断路器接线时，为使二次接线运行调试方便，下列安装单位的划分不正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当为线路一线路串时，每条出线作为一个安装单位，每台断路器为一个安装单位；",false,{"key":16,"text":17,"correct":14},"B","当为线路一变压器串时，变压器、出线，每台断路器各为一个安装单位；",{"key":19,"text":20,"correct":14},"C","当线路接有并联电抗器时，并联电抗器可单独作为一个安装单位，也可和线路合设一个安装单位；",{"key":22,"text":23,"correct":24},"D","每台断路器及变压器均可作为独立的安装单位。",true,"依据 DL\u002FT5136—2001第7.1.7条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]