[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1022008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1022008,751,1,"单选题","当最大机组容量为125MW及以下的发电厂以两种升高电压向用户供电或与电力系统连接时，其主变压器宜采用三绕组变压器，但每个绕组的通过功率应达到该变压器额定容量的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%以上；",false,{"key":16,"text":17,"correct":18},"B","15%以上；",true,{"key":20,"text":21,"correct":14},"C","20%以上；",{"key":23,"text":24,"correct":14},"D","30%以上。","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]