[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1021964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1021964,751,1,"单选题","发电厂主变压器容量及台数选择。 发电机容量60MW及以下，具有发电机电压母线的主变压器容量，不需满足的要求为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","具有发电机电压母线的主变压器，其容量应与接在发电机电压母线的发电机容量相匹配；",true,{"key":16,"text":17,"correct":18},"B","发电机电压母线的负荷为最小时，能将剩余有功和无功功率送入地区电力系统;",false,{"key":20,"text":21,"correct":18},"C","当发电机电压母线上的容量最大的一台发电机停运时，应能从电力系统受电，以满足发电机电压母线最大负荷的需要；",{"key":23,"text":24,"correct":18},"D","当发电厂为热电厂，因供热机组热负荷的变动而需要限制本厂出力时，应能从电力系统受电，以满足发电机电压母线的最大负荷的需要。","根据 DL5000—2000第13.1.4条。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]