[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1021952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1021952,751,1,"单选题","某发电厂发电机装机容量为2x 50MW，功率因数cosψ=0.85，额定电压为10.5kV，接线均为发电机，变压器组接上11OkV升压站，发电机回路和升压变压器绕组及1OkV导体的电容电流为11A。 该两台发电机中性点一般情况下应采用的接地方式为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","中性点不接地；",false,{"key":16,"text":17,"correct":14},"B","中性点直接接地；",{"key":19,"text":20,"correct":21},"C","中性点经消孤线圈接地（欠补偿方式）；",true,{"key":23,"text":24,"correct":14},"D","中性点经消弧线圈接地（过补偿方式）。","根据《导体和电器选择设计技术规定》（DL\u002FT 5222—2005）第18.1.6条之规定，宜采用欠补偿方式。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]