[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1021859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1021859,751,1,"单选题","某500kV变电所，所址海拔2100m， 500kV出线本期2回，最终6回；主变压器本期1组750MV A，最终2组，220kV出线本期8回，最终120。 该变电所220kV最终最合理的接线应为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一个半断路器接线；",false,{"key":16,"text":17,"correct":14},"B","双母线接线；",{"key":19,"text":20,"correct":21},"C","双母线单分段接线；",true,{"key":23,"text":24,"correct":14},"D","双母线双分段接线。","根据《220~500kV变电所设计技术规程》（DL\u002FT 5218—2005）第7.1.4条，220kV最终进出线14回。",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师发输变电专业","建筑工程",0]