[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},141119,75,1,"单选题","在采用成本加酬金合同价时，为了有效地控制工程投资，最好采用( )确定的合同价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最高限额成本加固定最大酬金",true,{"key":16,"text":17,"correct":18},"B","成本加固定百分比酬金",false,{"key":20,"text":21,"correct":18},"C","成本加固定金额",{"key":23,"text":24,"correct":18},"D","成本加奖罚","采用最高限额成本加固定最大酬金确定合同价时，首先要确定限额成本、报价成本和最低成本，当实际成本没有超过最低成本时，承包商花费的成本费用及应得酬金等都可得到业主的支持，并与业主分享节约额；如果实际工程成本在最低成本和报价成本之间，承包商只能得到成本和酬金；如果实际工程成本在报价成本与最高限额成本之间，则只能得到全部成本；实际工程成本超过最高限额成本时，则超过部分发包方不予支付。这种合同价形式有利于控制工程投资，并能鼓励承包商最大限度地降低工程成本。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]