[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},141103,75,1,"单选题","工程施工过程中一项或多项工作实际完成日期迟于计划完成日期，导致合同工期的延长，称为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期延误",true,{"key":16,"text":17,"correct":18},"B","工期推迟",false,{"key":20,"text":21,"correct":18},"C","工期滞后",{"key":23,"text":24,"correct":18},"D","工期顺延","工期延误是指工程施工过程中任何一项或多项工作实际完成日期迟于计划规定的完成日期，从而可能导致整个合同工期的延长；工程延误对合同双方一般都会造成损失。业主因工程延误不能及时交付使用，投入生产，就不能按计划实现投资效果，失去盈利机会，损失市场利润；承包商因工期延误会增加工程成本，生产效率降低，企业信誉受到影响，最终还可能导致合同规定的误期损害赔偿的处罚。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]