[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},141099,75,1,"单选题","在固定资产投资估算编制方法中，根据已建成的类似项目的投资额、生产能力和拟建项目的生产能力，估算拟建项目投资额的方法是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资金周转率法",false,{"key":16,"text":17,"correct":14},"B","设备费用百分比估算法",{"key":19,"text":20,"correct":21},"C","生产能力指数法",true,{"key":23,"text":24,"correct":14},"D","指标估算法","A项，资金周转率法是用资金周转率来推测投资额的一种简单方法；B项，设备费用百分比估算法是以拟建项目或装置的设备费为基数或以拟建项目中主要的或投资比重较大的工艺设备投资为基数来估算投资额；C项，生产能力指数法是根据已建成的、性质类似的建设项目或装置的投资额和生产能力，以及拟建项目或装置的生产能力估算其投资额；D项，指标估算法是依照各种具体工程和费用的造价指标(投资估算指标或概算指标)进行单位工程投资的估算。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]