[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141094":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141094,75,2,"多选题","网络计划调整的主要内容包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","关键线路长度的调整",true,{"key":16,"text":17,"correct":14},"B","非关键工作时差的调整",{"key":19,"text":20,"correct":21},"C","要求工期的调整",false,{"key":23,"text":24,"correct":14},"D","逻辑关系的调整",{"key":26,"text":27,"correct":14},"E","重新估计某些工作的持续时间以及对资源的投入作相应调整","ABDE","网络计划调整的主要内容有：①调整关键线路的长度；②调整非关键工作的时差；③增、减工作项目；④调整工作之间的逻辑关系；⑤重新估计某些工作的持续时间；⑥对资源的投入作相应调整。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]