[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141093":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141093,75,2,"多选题","投标报价的依据包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建设工程工程量清单计价规范",true,{"key":16,"text":17,"correct":14},"B","企业定额，国家或省级、行业建设主管部门颁发的计价定额",{"key":19,"text":20,"correct":14},"C","施工现场情况、工程特点及拟定的投标施工组织设计或施工方案",{"key":22,"text":23,"correct":14},"D","市场价格信息或工程造价管理机构发布的工程造价信息",{"key":25,"text":26,"correct":27},"E","拟定的招标文件及招标工程量清单",false,"ABCD","投标报价的依据包括：①建设工程工程量清单计价规范；②国家或省级、行业建设主管部门颁发的计价办法；③企业定额，国家或省级、行业建设主管部门颁发的计价定额；④招标文件、工程量清单及其补充通知、答疑纪要；⑤建设工程设计文件及相关资料；⑥施工现场情况、工程特点及拟定的投标施工组织设计或施工方案；⑦与建设项目相关的标准、规范等技术资料；⑧市场价格信息或工程造价管理机构发布的工程造价信息；⑨其他的相关资料。E项属于招标控制价据编制与复核的依据。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]