[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141070":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141070,75,2,"多选题","在工程建设项目招标的定标和履行过程中，下列说法错误的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","评标报告由评标委员会全体成员签字，对评标结论持有异议的评标委员会成员可以书面阐述其不同意见和理由",false,{"key":16,"text":17,"correct":14},"B","投标人或者其他利害关系人对依法必须进行招标的项目的评标结果有异议的，应当在中标候选人公示期间提出",{"key":19,"text":20,"correct":21},"C","招标人应当自签订中标合同之日起15日内，向有关行政监管部门提交招标投标情况的书面报告",true,{"key":23,"text":24,"correct":14},"D","中标人不得向他人转让中标项目，也不得将中标项目肢解后分别向他人转让",{"key":26,"text":27,"correct":21},"E","中标人按照合同约定或者经招标人同意，可以将中标项目的部分工作分包给他人完成","CE","C项，依法必须进行施工招标的项目，招标人应当自发出中标通知书15日内，向有关行政监督部门提交招标投标情况的书面报告；E项，中标人按照合同约定或者经招标人同意，可以将中标项目的部分非主体、非关键性工作分包给他人完成。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]