[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141068":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141068,75,2,"多选题","预算定额中人工工日消耗量的组成包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本用工",true,{"key":16,"text":17,"correct":18},"B","偶然用工",false,{"key":20,"text":21,"correct":18},"C","多余用工",{"key":23,"text":24,"correct":14},"D","人工幅度差",{"key":26,"text":27,"correct":14},"E","其他用工","ADE","预算定额中的人工工日消耗量是指在正常施工生产条件下，生产单位假定建筑安装产品(即分部分项工程或结构件)必须消耗的某种技术等级的人工工日数量。预算定额中人工工日消耗量由分项工程所综合的各个工序施工劳动定额包括的基本用工、其他用工以及施工劳动定额同预算定额工日消耗量的幅度差三部分组成。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]