[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141067":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141067,75,2,"多选题","下列费用中，应列入建筑安装工程措施项目费的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","社会保障费",false,{"key":16,"text":17,"correct":14},"B","职工教育经费",{"key":19,"text":20,"correct":21},"C","脚手架费",true,{"key":23,"text":24,"correct":21},"D","夜间施工费",{"key":26,"text":27,"correct":21},"E","施工排水、降水费","CDE","建筑安装工程费按照工程造价形成由分部分项工程费、措施项目费、其他项目费、规费、税金组成。其中，措施项目费是指为完成建设工程施工，发生于该工程施工前和施工过程中的技术、生活、安全、环境保护等方面的费用，内容包括：①安全文明施工费；②夜间施工增加费；③二次搬运费；④冬雨季施工增加费；⑤已完工程及设备保护费；⑥工程定位复测费：⑦特殊地区施工增加费；⑧大型机械设备进出场及安拆费；⑨脚手架工程费。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]