[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141064":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141064,75,2,"多选题","下列内容中，属于监理工程师在施工阶段投资控制任务的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制订建设工程资金使用计划",false,{"key":16,"text":17,"correct":18},"B","严格控制工程变更",true,{"key":20,"text":21,"correct":18},"C","做好工程计量工作",{"key":23,"text":24,"correct":18},"D","及时处理费用索赔",{"key":26,"text":27,"correct":18},"E","按合同规定提供材料和设备","BCDE","为完成施工阶段投资控制的任务，监理工程师应做好以下工作：①制订本阶段资金使用计划，并严格进行付款控制，做到不多付、不少付、不重复付；②严格控制工程变更，力求减少变更费用；③制定预防费用索赔的措施，以避免或减少索赔数额；④根据有关合同的要求，协助做好应由业主方完成的、与工程进展密切相关的各项工作，如按期提交合格施工现场，按质、按量、按期提供材料和设备等工作；⑤做好工程计量工作；⑥审核施工单位提交的工程结算书等。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]