[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141049":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141049,75,2,"多选题","监理工程师在施工阶段进度控制的工作有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对建设工程进度分目标进行论证",false,{"key":16,"text":17,"correct":18},"B","完善建设工程控制性施工进度计划",true,{"key":20,"text":21,"correct":14},"C","编制承包方材料和设备采购计划",{"key":23,"text":24,"correct":18},"D","研究制定预防工期索赔的措施",{"key":26,"text":27,"correct":18},"E","做好对人力、材料、机具、设备等的投入控制工作","BDE","为完成施工阶段的进度控制任务，监理工程师应当做好以下工作：①根据施工招标和施工准备阶段的工程信息，迸一步完善建设工程控制性进度计划，并据此进行施工阶段进度控制；②审核阶段性施工进度计划及其与总进度目标的一致性；③制定业主方材料和设备供应进度计划并进行控制，使其满足施工要求；④审查施工单位进度控制报告，督促施工单位做好施工进度控制；⑤对施工进度进行跟踪检查，掌握施工动态；⑥制定预防工期索赔的措施，做好工期索赔工作；⑦在施工过程中，做好对人力、材料、机具、设备等的投入控制工作、信息反馈工作、对比和纠偏工作，使进度控制定期连续进行；⑧召开进度协调会议，及时协调有关各方关系，使工程施工顺利进行。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]