[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141036":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141036,75,2,"多选题","建设工程质量控制应避免不断提高质量目标的倾向，要避免这种倾向，应( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对目标有理性的认识",true,{"key":16,"text":17,"correct":18},"B","追求“最新”、“最高”、“最好”的目标",false,{"key":20,"text":21,"correct":18},"C","对投资太大的工程放弃不建",{"key":23,"text":24,"correct":14},"D","在工程建设早期要有前瞻性的确定质量目标",{"key":26,"text":27,"correct":14},"E","定量分析提高质量目标后对投资目标和进度目标的影响","ADE","要避免不断提高质量目标的倾向，应该做的工作包括：①在工程建设早期确定质量目标时应有一定的前瞻性；②对质量目标要有一个理性的认识，不应盲目追求“最新”、“最高”、“最好”等目标；③要定量分析提高质量目标后对投资目标和进度目标的影响。在这一前提下，即使确实有必要适当提高质量标准，也应将对投资目标和进度目标的不利影响减少到最低程度。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]