[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141032":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141032,75,2,"多选题","索赔费用的组成要素一般应包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","人工费、材料费",true,{"key":16,"text":17,"correct":14},"B","施工现场管理费",{"key":19,"text":20,"correct":14},"C","利息和利润",{"key":22,"text":23,"correct":14},"D","分包费、总部管理费",{"key":25,"text":26,"correct":27},"E","不可抗力导致的施工机具损坏费",false,"ABCD","索赔费用的组成要素可涉及人工费、材料费、使用机具使用费、分包费、施工现场管理费、总部管理费、利息和利润等。E项，因不可抗力事件导致的人员伤亡、财产损失及其费用增加，如属于承包人的施工机械设备损坏及停工损失引起的，应由承包人承担。因此，由于不可抗力引起的施工机具损坏，应由施工单位自己承担，不能进行索赔。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]