[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141030":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141030,75,2,"多选题","在投资估算与概算中，基本预备费的计算基数应包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设备及工器具购置费",true,{"key":16,"text":17,"correct":14},"B","建筑安装工程费用",{"key":19,"text":20,"correct":14},"C","工程建设其他费用",{"key":22,"text":23,"correct":24},"D","建设期贷款利息",false,{"key":26,"text":27,"correct":24},"E","固定资产投资方向调节税","ABC","基本预备费是指在项目实施中可能发生的难以预料的支出，需要预先预留的费用，又称不可预见费。它主要指设计变更及施工过程中可能增加工程量的费用。基本预备费=(设备及工器具购置费+建筑安装工程费用+工程建设其他费用)×基本预备费率。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]