[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141026":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141026,75,2,"多选题","下列建设工程实施过程发生的事件中，属于业主或投资者风险的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","资金筹措无门",true,{"key":16,"text":17,"correct":14},"B","投资回收期长",{"key":19,"text":20,"correct":21},"C","由于承包商技术错误造成的直接损失",false,{"key":23,"text":24,"correct":14},"D","工程所在国发生全国性罢工",{"key":26,"text":27,"correct":21},"E","承包商克扣工人工资，引起公愤导致群体行为","ABD","对于项目业主或投资商，通常遇到的风险主要有人为风险、经济风险、自然风险以及一些特殊风险。A项属于人为风险；B项属于经济风险：CE两项属于承包商的风险；D项属于特殊风险。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]