[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141015":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141015,75,2,"多选题","工程网络计划的计划工期的确定方法是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","已规定要求工期时，计划工期总是小于要求工期",false,{"key":16,"text":17,"correct":18},"B","未规定要求工期时，计划工期等于计算工期",true,{"key":20,"text":21,"correct":18},"C","已规定要求工期时，计划工期不超过要求工期",{"key":23,"text":24,"correct":14},"D","未规定要求工期时，计划工期小于计算工期",{"key":26,"text":27,"correct":14},"E","已规定要求工期时，计划工期总是等于要求工期","BC","",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]