[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141005,75,2,"多选题","由于业主提供的图纸有缺陷，导致工程暂停15天，则承包商可以提出索赔的内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","利润",false,{"key":16,"text":17,"correct":18},"B","人员窝工费",true,{"key":20,"text":21,"correct":18},"C","机械窝工费",{"key":23,"text":24,"correct":18},"D","增加的现场管理费",{"key":26,"text":27,"correct":18},"E","延误的工期","BCDE","可提出利润索赔的情况主要包括：①工程范围变更；②发包人提供的文件有缺陷或错误；③发包人未能提供施工场地以及因发包人违约导致的合同终止等。工程的延误是由于业主提供的图纸有缺陷，该问题属于业主原因造成的工期拖延，因此承包商可以索赔人员、机械的窝工费，现场管理费以及由此拖延的工期，但承包商不能因此索赔利润。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]