[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-141004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},141004,75,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有多个终点节点",false,{"key":16,"text":17,"correct":18},"B","有多个起点节点",true,{"key":20,"text":21,"correct":14},"C","工作代号重复",{"key":23,"text":24,"correct":18},"D","有多余的虚工作",{"key":26,"text":27,"correct":18},"E","节点编号有误","BDE","双代号网络图绘制的基本规则包括：①必须正确表达已定的逻辑关系。②严禁出现循环回路。③在节点之间严禁出现带双向箭头或无箭头的连线。④严禁出现没有箭头节点或没有箭尾节点的箭线。⑤某些节点有多条外向箭线或多条内向箭线时，为使图形简洁，可使用母线法绘制。⑥绘制网络图时，箭线不宜交叉；当交叉不可避免时，可用过桥法或指向法表示。⑦图中应只有一个起点节点和一个终点节点，其他所有节点均应是中间节点。AB两项，图中终点节点是⑨，而起点节点有①②两个；CD两项，该图中并没有工作代号重复，②一③与②一④之间的虚工作是多余的；E项，⑥一⑤的箭尾节点的编号大于其箭头节点的编号。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]