[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140998,75,2,"多选题","",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","①—②—④一⑥—⑧—⑨",true,{"key":16,"text":17,"correct":14},"B","①—②—⑤一⑥—⑧—⑨",{"key":19,"text":20,"correct":21},"C","①—②—⑦一⑧—⑨",false,{"key":23,"text":24,"correct":14},"D","①—②—④一⑥—⑦—⑧一⑨",{"key":26,"text":27,"correct":14},"E","①—②—⑤一⑥一⑦—⑧一⑨","ABDE","自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路为关键线路。A项，总的工作持续时间为：9+15+5+5+2=36；B项，总的工作持续时间为：9+14+6+5+2=36；C项，总的工作持续时间为：9+17+2+2=30；D项，总的工作持续时间为：9+15+5+3+2+2=36；E项，总的工作持续时间为：9+14+6+3+2+2=36。因此，ABDE四项的线路均为关键线路。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]