[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140997":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140997,75,2,"多选题","下列建设项目评价指标中，可用于选择互斥投资方案的指标有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","净现值",true,{"key":16,"text":17,"correct":14},"B","追加投资收益率",{"key":19,"text":20,"correct":14},"C","差额的净将来值",{"key":22,"text":23,"correct":24},"D","投资利润率",false,{"key":26,"text":27,"correct":24},"E","总投资收益率","ABC","互斥方案的选择标准有很多，例如净现值、净年值、净将来值法，差额的净现值、净年值、净将来值法，追加投资收益率法等。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]