[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140992,75,2,"多选题","下列各项可导致人为风险的是( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","体制法规不合理",true,{"key":16,"text":17,"correct":14},"B","道德风险",{"key":19,"text":20,"correct":14},"C","工期拖延",{"key":22,"text":23,"correct":14},"D","监理工程师失职",{"key":25,"text":26,"correct":27},"E","投资环境差劣",false,"ABCD","人为风险包括：①政府或主管部门的政策和行为；②体制法规不合理；③主管部门设置障碍；④资金筹措无门；⑤不可预见事件；⑥合同条款不严谨；⑦道德风险；⑧群体行为越轨；⑨承包商缺乏合作诚意；⑩承包商履约不力或不履约；⑾工期拖延；⑿材料供应商履约不力或违约；⒀指定分包商履约不力；⒁监理工程师失职；⒂设计错误。E项属于业主或投资商通常遇到的经济风险之一。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]