[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140984":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140984,75,2,"多选题","下列各项属于与项目建设有关的其他费用的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设单位管理费",true,{"key":16,"text":17,"correct":14},"B","工程监理费",{"key":19,"text":20,"correct":14},"C","勘察设计费",{"key":22,"text":23,"correct":24},"D","供电贴费",false,{"key":26,"text":27,"correct":24},"E","施工机构迁移费","ABC","与项目建设有关的其他费用包括建设单位管理费、勘察设计费、研究试验费、临时设施费、工程监理费、工程保险费、引进技术和进口设备其他费和工程承包费。原先包括在与项目建设有关的其他费用中的供电贴费和施工机构迁移费已停止征收。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]