[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140981":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140981,75,2,"多选题","",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作B将使工期拖延3周",false,{"key":16,"text":17,"correct":14},"B","工作C将使工期拖延1周",{"key":19,"text":20,"correct":21},"C","工作D将使工期拖延2周",true,{"key":23,"text":24,"correct":21},"D","工作C不影响工期和紧后工作",{"key":26,"text":27,"correct":21},"E","工作B将使工期拖延2周、紧后工作最早开始时间推迟3周","CDE","该双代号时标网络计划的关键线路为：D→F→I，总工期为12周。由实际进度前锋线可知，AE两项，在第6周末时，B工作拖后三周，由于B工作有一周的总时差，所以会使工期拖延2周，紧后工作H工作最早开始时间推迟3周；BD两项，第6周末时，C工作已完工，不影响工期和紧后工作；C项，D工作在关键线路上，是关键工作，其进度拖延2周会导致工期拖延2周。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]