[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140968":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140968,75,2,"多选题","某工程网络计划中，已知工作M的自由时差为4天。在该网络计划执行过程中，工作M的实际进度比原计划延后了2天，其他工作正常。则此时工作M( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不会使总工期延长",true,{"key":16,"text":17,"correct":14},"B","不影响其后续工作的正常进行",{"key":19,"text":20,"correct":21},"C","总时差不变，自由时差减少2天",false,{"key":23,"text":24,"correct":14},"D","总时差和自由时差各减少2天",{"key":26,"text":27,"correct":21},"E","自由时差不变，总时差减少2天","ABD","自由时差，是指在不影响其紧后工作最早开始的前提下，本工作可以利用的机动时间。已知工作M的自由时差为4天，工作M的实际进度比原计划延后了2天，所以，其后续工作不会受到影响。总时差，是指在不影响总工期的前提下，本工作可以利用的机动时间。由于工作M的进度不会影响其后续工作，因此也不会影响总工期，但其自由时差变为2天，同时总时差也减少2天。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]