[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140952":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140952,75,2,"多选题","网络计划调整时，非关键工作在其时差范围内进行调整的目的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","更充分地利用资源",true,{"key":16,"text":17,"correct":18},"B","缩短非关键工作的持续时间",false,{"key":20,"text":21,"correct":14},"C","降低工程成本",{"key":23,"text":24,"correct":14},"D","满足工程施工的需要",{"key":26,"text":27,"correct":18},"E","缩短项目的总工期","ACD","非关键工作时差的调整应在其拥有的时差的范围内进行，以便更充分地利用资源、降低工程成本或满足施工的需要。每一次对非关键工作进行调整后都必须重新计算其时间参数，并观察该调整对计划全局的影响。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]