[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140951":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140951,75,2,"多选题","依照《建设工程工程量清单计价规范》(GB50500-2013)的规定，以下( )事项(但不限于)发生时，发承包双方应当按照合同约定调整合同价。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","法律法规变化",true,{"key":16,"text":17,"correct":14},"B","工程变更",{"key":19,"text":20,"correct":21},"C","工程进度变化",false,{"key":23,"text":24,"correct":14},"D","不可抗力",{"key":26,"text":27,"correct":14},"E","工程量清单缺项","ABDE","根据《建设工程工程量清单计价规范》(GB50500-2013)的规定，以下事项(但不限于)发生时，发承包双方应当按照合同约定调整合同价款：①法律法规变化；②工程变更；③项目特征描述不符；④工程量清单缺项；⑤工程量偏差；⑥计日工；⑦物价变化；⑧暂估价；⑨不可抗力；⑩提前竣工(赶工补偿)；误期赔偿；索赔；现场签证；暂列金额。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]