[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140950":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140950,75,2,"多选题","设备安装工程概算的编制方法包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","预算单价法",true,{"key":16,"text":17,"correct":14},"B","扩大单价法",{"key":19,"text":20,"correct":14},"C","概算指标法",{"key":22,"text":23,"correct":24},"D","概算定额法",false,{"key":26,"text":27,"correct":24},"E","类似工程预决算法","ABC","单位工程概算分为建筑工程概算和设备及安装工程概算两大类。设备安装工程概算的编制方法包括：①预算单价法。当初步设计有详细设备清单时，可直接按预算价编制设备安装单位工程概算。②扩大单价法。当初步设计的设备清单不完备，或仅有成套设备的质量时，可采用主体设备、成套设备或工艺线的综合扩大安装单价编制概算。③概算指标法。当初步设计的设备清单不完全或安装预算单价及扩大综合单价不全，无法采用预算单价法和扩大单价法时，可采用概算指标编制概算。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]