[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140945":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140945,75,2,"多选题","下列关于发售资格预审文件和招标文件的说法中，正确的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","资格预审文件或者招标文件的发售期不得少于5日",true,{"key":16,"text":17,"correct":14},"B","依法必须进行招标的项目提交资格预审申请文件的时间，自资格预审文件停止发售之日起不得少于5日",{"key":19,"text":20,"correct":14},"C","招标人可以对已发出的招标文件进行必要的澄清或者修改",{"key":22,"text":23,"correct":24},"D","潜在投标人对资格预审文件有异议的，应当在提交资格预审申请文件截止时间3日前提出",false,{"key":26,"text":27,"correct":14},"E","招标人发售招标文件收取的费用用于补偿印刷、邮寄的成本支出","ABCE","D项，潜在投标人或者其他利害关系人对资格预审文件有异议的，应当在提交资格预审申请文件截止时间2日前提出；对招标文件有异议的，应当在投标截止时间10日前提出。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]