[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140940":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":9},140940,75,1,"单选题","",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差为零，总时差必定为零",false,{"key":16,"text":17,"correct":18},"B","总时差为零，自由时差必定为零",true,{"key":20,"text":21,"correct":14},"C","在不影响紧后工作最迟开始前提下，工作的机动时间为其自由时差",{"key":23,"text":24,"correct":14},"D","在不影响紧后工作最早开始前提下，工作的机动时间为其总时差",{"id":6,"name":26,"category":27,"favorite":28},"(高级) 建筑与房地产经济","经济金融",0]