[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},140937,75,1,"单选题","对建设工程项目目标进行主动控制的主要作用在于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量检查",false,{"key":16,"text":17,"correct":18},"B","防忠于未然",true,{"key":20,"text":21,"correct":14},"C","事中控制",{"key":23,"text":24,"correct":14},"D","进度纠偏","主动控制是一种事前控制。它是在计划实施之前就采取控制措施，以降低目标偏离的可能性或其后果的严重程度，起到防患于未然的作用。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]