[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},140934,75,1,"单选题","审查施工组织设计、审查确认施工分包单位是( )的任务。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工招标阶段",false,{"key":16,"text":17,"correct":14},"B","施工阶段投资控制",{"key":19,"text":20,"correct":14},"C","施工阶段进度控制",{"key":22,"text":23,"correct":24},"D","施工阶段质量控制",true,"为完成施工阶段质量控制任务，监理工程师应当做好以下工作：①协助业主做好施工现场准备工作，为施工单位提交质量合格的施工现场；②确认施工单位资质；③审查确认施工分包单位；④做好材料和设备检查上作，确认其质量；⑤检查施工机械和机具，保证施工质量；⑥审查施工组织设计；⑦检查工序质量，严格工序交接检查制度；⑧做好各项隐蔽工程的检查工作；⑨做好工程变更方案的比选，保证工程质量；⑩进行质量监督，行使质量监督权；⑾认真做好质量鉴证工作；⑿行使质量否决权，协助做好付款控制；⒀组织质量协调会；⒁做好中间质量验收准备工作；⒂做好竣工验收工作；⒃审核竣工图等。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]