[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},140928,75,1,"单选题","在工程网络计划执行过程中，如果只发现工作P出现进度拖延，且拖延的时间超过其总时差，则( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将使工程总工期延长",true,{"key":16,"text":17,"correct":18},"B","不会影响其后续工作的原计划安排",false,{"key":20,"text":21,"correct":18},"C","不会影响其紧后工作的总时差",{"key":23,"text":24,"correct":18},"D","工作P不会变为关键工作","该工作的拖延时间超过总时差时会使总工期延长，若拖延时间只超过某工作的自由时差时，会影响该工作的紧后工作而不会影响总工期。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]