[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},140919,75,1,"单选题","进度控制的目标是在满足投资和质量要求的前提下，力求使整个建设工程按计划的时间动用。对于民用项目来说，就是要按计划时间达到( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收",false,{"key":16,"text":17,"correct":18},"B","交付使用",true,{"key":20,"text":21,"correct":14},"C","负荷联动试车成功",{"key":23,"text":24,"correct":14},"D","实际工期不超过计划工期","建设工程进度控制的目标是指通过有效的进度控制工作和具体的进度控制措施，在满足投资目标和质量要求的前提下，力求使工程实际工期不超过计划工期。但是，进度控制往往更强调对整个建设工程总工期的控制，使工程按计划的时间投入使用(投产或交付使用)。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]