[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140831":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140831,75,2,"多选题","基于BIM技术的成本管理流程有（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程预算",true,{"key":16,"text":17,"correct":14},"B","5D模型建立",{"key":19,"text":20,"correct":14},"C","成本控制与分析",{"key":22,"text":23,"correct":14},"D","工程结算",{"key":25,"text":26,"correct":27},"E","竣工决算",false,"ABCD","本题考查B1M技术的成本管理流程。 基于BIM技术的成本管理流程:工程预算、5D模型建立、成本控制与分析、工程结算。 E选项说法错误，应是工程结算。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]