[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140816":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140816,75,2,"多选题","BIM应用策划对工程项目BIM实施的作用体现为（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","提供一个用于后续参与者的BIM行为基准",true,{"key":16,"text":17,"correct":14},"B","为测量项目目标和过程管控提供基准线",{"key":19,"text":20,"correct":14},"C","对整个项目团队而言，全面策划有助于减少项目的全程风险而获得收益",{"key":22,"text":23,"correct":24},"D","提供了更高的准入门槛",false,{"key":26,"text":27,"correct":14},"E","有助于BIM团队清晰理解项目BIM应用的目标","ABCE","本题考查的是BIM应用策划概述。 BIM应用策划对工程项目的BIM实施的作用体现为：有助于BIM团队清晰理解项目BIM应用的目标，规范BIM应用流程，规范BIM实施所需要的附加资源，培训等内容，提供一个用于后续参与者的BIM行为基准，为测量项目目标和过程管控提供基准线，对整个项目团队而言，全面策划有助于减少项目的全程风险而获得收益。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]