[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140813":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140813,75,2,"多选题","基于BIM技术的成本管理流程中的成本控制与分析包含（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制目标成本和计划",true,{"key":16,"text":17,"correct":14},"B","编制材料计划",{"key":19,"text":20,"correct":14},"C","工程量申报",{"key":22,"text":23,"correct":14},"D","辅助变更管理",{"key":25,"text":26,"correct":27},"E","竣工结算办理",false,"ABCD","本题考查基于BIM技术的成本管理。 成本控制与分析：编制目标成本和计划，编制材料计划，工程量申报，辅助变更管理，基于BIM技术的动态成本分析。 E选项为混淆选项。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]