[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140748":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140748,75,2,"多选题","建设项目工程总承包的方式主要有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计-施工总承包",true,{"key":16,"text":17,"correct":18},"B","采购施工总承包",false,{"key":20,"text":21,"correct":18},"C","施工总承包",{"key":23,"text":24,"correct":18},"D","勘察设计总承包",{"key":26,"text":27,"correct":14},"E","设计采购施工总承包","AE","本题考查的是施工总承包。 建设项目工程总承包主要有两种方式：①设计-施工总承包，是指工程总承包单位按照合同约定，承担工程项目设计和施工，并对承包工程的质量、安全、工期、造价全面负责；②设计采购施工总承包(简称EPC)，是指工程总承包单位按照合同约定，承担工程项目的设计、采购、施工、试运行服务等工作，并对承包工程的质量、安全、工期、造价全面负责。 其余选项为混淆选项。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]