[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},140732,75,1,"单选题","下列构成合同文件的优先顺序正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①合同协议书;②投标函及其附录（如果有）;③中标通知书（如果有）;④专用合同条款及其附件;⑤通用合同条款;⑥技术标准和要求;⑦图纸;",false,{"key":16,"text":17,"correct":18},"B","①合同协议书;②中标通知书（如果有）;③投标函及其附录（如果有）;④专用合同条款及其附件;⑤通用合同条款;⑥技术标准和要求;⑦图纸;",true,{"key":20,"text":21,"correct":14},"C","①合同协议书;②中标通知书（如果有）;③专用合同条款及其附件;④投标函及其附录（如果有）;⑤通用合同条款;⑥技术标准和要求;⑦图纸;",{"key":23,"text":24,"correct":14},"D","①合同协议书;②专用合同条款及其附件;③投标函及其附录（如果有）;④中标通知书（如果有）;⑤通用合同条款;⑥技术标准和要求;⑦图纸;","构成合同文件的优先顺序 ①合同协议书; ②中标通知书（如果有）; ③投标函及其附录（如果有）; ④专用合同条款及其附件; ⑤通用合同条款; ⑥技术标准和要求; ⑦图纸;",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]