[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140716":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140716,75,2,"多选题","国民经济评价着眼于项目对社会提供的有用产品和服务，以及项目所耗费的全社会的用资源来考察项目的效益和费用，因此，效益和费用中不包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","间接效益",false,{"key":16,"text":17,"correct":18},"B","税金",true,{"key":20,"text":21,"correct":18},"C","国内贷款利息",{"key":23,"text":24,"correct":14},"D","间接费用",{"key":26,"text":27,"correct":18},"E","补贴","BCE","此题考查建设项目经济评价。 国民经济评价着眼于项目对社会提供的有用产品和服务，以及项目所耗费的全社会的有用资源来考察项目的效益和费用，因此，效益和费用中不包括税金、国内贷款利息、补贴。 A和D选项是混淆选项，不必掌握。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]