[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},140683,75,1,"单选题","采用强制确定法对某工程四个分部工程进行价值工程对象的选择时,各分部工程的功能系数和成本系数如下表.根据计算,应优先选择为价值工程对象的分部工程是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲",false,{"key":16,"text":17,"correct":18},"B","乙",true,{"key":20,"text":21,"correct":14},"C","丙",{"key":23,"text":24,"correct":14},"D","丁","价值系数＝功能评价系数\u002F成本系数,当价值系数等于１时,评价对象的功能重要程度与成本的比重属于合理匹配,可以认为功能的目前成本是比较合理的。本题中工程乙的价值系数等于１,应优先选择为价值工程对象。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]