[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140679":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140679,75,2,"多选题","建设项目可行性研究包括( )等阶段。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":18},"B","机会研究",true,{"key":20,"text":21,"correct":18},"C","初步可行性研究",{"key":23,"text":24,"correct":18},"D","最终可行性研究",{"key":26,"text":27,"correct":18},"E","项目的评估和决策","BCDE","此题考查建设项目可行性研究的阶段和内容。 生产性工程建设项目从筹备建设到建成投产，直至保费，其发展过程大体可以分为三个时期，即建设准备时期（规划时期，也称投资前期）、建设时期（也称投资时期或实施阶段）、生产时期。建设项目可行性研究可分为机会研究、初步可行性研究、最终可行性研究和项目的评估和决策四个阶段。 A选项为混淆选项。",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 建筑与房地产经济","经济金融",0]