[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140666":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},140666,75,1,"单选题","价值工程中的全寿命周期费用是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","研究和生产全过程发生的全部成本",false,{"key":16,"text":17,"correct":14},"B","从开始使用至报废过程中发生的费用总和",{"key":19,"text":20,"correct":14},"C","产品存续期的总成本",{"key":22,"text":23,"correct":24},"D","生产费用和使用费用之和",true,"价值工程中的全寿命周期费用是指生产费用和使用费用之和。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 建筑与房地产经济","经济金融",0]